SOLAR OWNERS AND INSTALLERS

Solar SSEG registration, lodged and chased

Every grid-connected solar or battery system must be registered with the electricity supplier, whether or not it exports a single unit. Eskom has cut its list to three documents and waived its fees for systems up to 50 kVA until 30 September 2026. The application still gets refused for an inverter that is not on the list, a certificate that does not cover the solar circuit, or a test report signed by the wrong person. We check all three against the supplier’s current requirements, lodge the application, and chase it to the approval and the meter appointment.

R890our fee per site · supplier fees, where any apply, paid to the supplier · Eskom fees waived up to 50 kVA until 30 September 2026
3 documentsthe certificate of compliance, the NRS 097-2-1 inverter certificate and the test report, all checked before lodging
Eskom or municipalwe lodge with whoever sends your electricity bill, on their form and their list
R0 supplier feesfor Eskom systems up to 50 kVA registered before 30 September 2026

What actually goes wrong

What you get for R890

How it works

  1. 1Order and upload the three documentsPlus your electricity account number and the inverter make and model.
  2. 2We check and tell you if anything is missingWithin two working days. If the pack is complete we lodge straight away.
  3. 3Lodged, chased, approvedWe follow the application to the approval letter and the meter appointment and send you both.
Register my solar

Not sure this is the right one for you? Ask us first and you get a written answer within one business day.

What we will need from you

Frequently asked questions

Is there a supplier fee on top?

For Eskom customers with systems up to 50 kVA, no: Eskom has waived registration and connection fees and the smart meter until 30 September 2026. After that, or for larger systems and for municipalities that charge, the supplier’s quotation, connection and meter fees are paid to the supplier and are separate from our R890.

Can you register a system that has no certificate of compliance?

No supplier will accept it, so no. If your installer did not issue a supplementary certificate for the solar circuit, we tell you what is missing and, if you want, find a registered person to inspect and certify. That inspection is separate from this service.

My inverter is not on the NRS 097-2-1 list. What happens?

We check the list before we lodge, and if the model is not on it we tell you before you pay anything to a supplier. An unlisted inverter is refused; the options are a type test certificate from the manufacturer, if one exists, or replacing the inverter.

Do installers use this service?

Yes. Installers who want to hand over a registered system without running the application themselves order it per site, and we work from their certificate and test report. We can invoice the installer or the customer.

Related

We prepare and lodge the application under your written authority. The supplier decides whether to approve the connection, and its fees are separate. Sources: Eskom’s SSEG page and its statement of 26 March 2026; the Electrical Installation Regulations, 2009; NRS 097-2-1. This is information, not legal advice.